Major/Minor
Milestones
|
Tasks
(Additional tasks to be added/modified
as per project needs)
|
|
1
|
QA Resource Onboarding
|
|
|
1.1
|
|
QA Team Onboarding
|
|
1.2
|
|
System and Environment Access Provided
|
|
2
|
Test Planning
|
|
|
2.1
|
Requirement Analysis
|
Tasks/Dependency
|
|
BRD Walkthrough
|
|
SAD Walkthrough
|
|
NFR Requirements & Gap Analysis
|
|
Walkthrough Completed
|
|
2.2
|
Test Strategy
|
Draft
|
|
Review with SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
Test Strategy Sign off
|
|
2.3
|
SIT Test Plan
|
Draft
|
|
Review with QA/SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
Test Plan Sign off
|
|
2.4
|
Performance Test Planning
|
Draft Test Plan document preparation
|
|
Performance Scop/Scenario preparation and review
|
|
Workload Model
|
|
Review with QA/SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
Engage Support(Customer Infra, Networking, Application) team for
performance monitoring
|
|
Engage support team for databack/restore required and duration
|
|
Test Plan Sign off
|
|
2.5
|
QA-De-identification Strategy
|
Draft
|
|
Review with QA/SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
DI-Strategy Sign off
|
|
2.6
|
Test Data Generation
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3
|
Test Case Design
|
|
|
3.1
|
Test Coverage Matrix
|
Dependency
|
|
Draft
|
|
Review with QA/SM
|
|
3.2
|
Functional Test Cases
|
Prepare Draft test cases
|
|
Review with QA team
|
|
Upload in HP-ALM
|
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3.3
|
Integration Test Cases
|
Prepare Draft test cases
|
|
Review with QA team
|
|
Upload in HP-ALM
|
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3.4
|
End-End Test Cases
|
Prepare Draft test cases
|
|
Review with QA team
|
|
Upload in HP-ALM
|
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3.5
|
ETL/Reporting Test Cases
|
Prepare Draft test cases
|
|
Review with QA team
|
|
Upload in HP-ALM
|
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3.6
|
Regression Test Cases
|
Prepare Draft test cases
|
|
Review with QA team
|
|
Upload in HP-ALM
|
|
Identify Test data from Data profiles
|
|
Create Test Data
|
|
3.7
|
Performance Test Design & Scripting
|
Understanding the workflow
|
|
Creation/development scripting for workflow
|
|
Enhancing/Customizing script
|
|
Validation in SIT/Perf env
|
|
Update data parameter file for each script
|
|
Validation of existing scripts
|
|
Existing script maintenance
|
|
|
|
Test Data Identification and Creation/Set up
|
|
4
|
Test Automation
|
|
|
4.1
|
Test Script Preparation
|
Identify automation test cases
|
|
Enable/set framework and access
|
|
Test script draft
|
|
Existing script identification
|
|
Existing script Maintenance
|
|
5
|
Environment Readiness – QA
|
|
|
5.1
|
Environment Readiness
|
Key dependency
|
|
Submit Smartsheet – Environment Intake
|
|
Access raised and completed
|
|
Test Data required for Batch
|
|
Smoke Testing
|
|
5.2
|
Performance Environment Readiness
|
Submit Smartsheet – Environment Intake and Data Back up’s
|
|
Code Deployment into Perf env (as applicable)
|
|
Configuration changes and Pre requisite required.
|
|
Data Backup (Gold/Platinum/Titanium)
|
|
Environment shakedown testing
|
|
6
|
Test Execution – SIT
|
|
|
6.1
|
Cycle_1
|
Dependency
|
|
Application Test Cases
|
|
Integration Test Cases
|
|
ETL/Reporting Test Cases
|
|
Defect Remediation
|
|
6.2
|
Cycle_2
|
Dependency
|
|
Application Test Cases
|
|
Integration Test Cases
|
|
ETL/Reporting Test Cases
|
|
Defect Remediation
|
|
6.3
|
Cycle_3(Regression)
|
Clean Regression
|
|
Defect Remediation
|
|
6.4
|
BAT Support
|
Support Bat Test Plan
|
|
Support BAT HPALM activities
|
|
Defect Triage
|
|
Test Data for BAT
|
|
6.5
|
PPD Testing
|
Dependency
|
|
PPD Project Regression Testing
|
|
6.6
|
Performance Testing – Baseline Testing
|
Execute Baseline Scripts
|
|
Performance Monitoring and Metric
|
|
Results validation
|
|
Defect Remediation
|
|
Data Restore
|
|
6.7
|
Performance Testing – Cycle 1(multiple Runs)
|
Execute Cycle 1
|
|
Performance Monitoring and Metric analysis
|
|
Results validation
|
|
Defect Remediation
|
|
Data Backup/Restore
|
|
6.8
|
Performance Testing – Cycle 2(multiple Runs)
|
Execute Cycle 2
|
|
Performance Monitoring and Metric
|
|
Results validation
|
|
Draft
|
|
Data Backup/Restore
|
|
6.9
|
Roll back testing
|
Dependency
|
|
Baseline testing
|
|
Rollback testing
|
|
7
|
Test Closure
|
|
|
7.1
|
SIT Test Summary Closure Report & Sign off
|
Draft
|
|
Review with QA/SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
SIT Closure report Sign off
|
|
7.2
|
Performance Test Closure
|
Consolidation of Perf monitoring metrics/Loadrunner results
|
|
Draft
|
|
Review with QA/SM
|
|
Review with IT Project team
|
|
Review with Business
|
|
Performance Closure report Sign off
|
|
8
|
Production Readiness
|
|
|
8.1
|
QA Production Checklist
|
Draft
|
|
Review with QA/SM and Sign off from SM
|
|
Review with Production readiness team
|
|
Closure
|
|
8.2
|
Knowledge Transfer
|
KT/Transition to Product QA Team
|
|
All Project Related document in Teams path
|
|
9
|
Warranty Support
|
|
|
9.1
|
Warranty Support
|
Warranty release activities
|
|
|
|
|