QA Project Plan

 QA Project Plan

#

Major/Minor Milestones

Tasks

(Additional tasks to be added/modified as per project needs)

1

QA Resource Onboarding

 

1.1

 

QA Team Onboarding

1.2

 

System and Environment Access Provided

2

Test Planning

 

2.1

Requirement Analysis

Tasks/Dependency

BRD Walkthrough

SAD Walkthrough

NFR Requirements & Gap Analysis

Walkthrough Completed

2.2

Test Strategy

Draft

Review with SM

Review with IT Project team

Review with Business

Test Strategy Sign off

2.3

SIT Test Plan

Draft

Review with QA/SM

Review with IT Project team

Review with Business

Test Plan Sign off

2.4

Performance Test Planning

Draft Test Plan document preparation

Performance Scop/Scenario preparation and review

Workload Model

Review with QA/SM

Review with IT Project team

Review with Business

Engage Support(Customer Infra, Networking, Application) team for performance monitoring

Engage support team for databack/restore required and duration

Test Plan Sign off

2.5

QA-De-identification Strategy

Draft

Review with QA/SM

Review with IT Project team

Review with Business

DI-Strategy Sign off

2.6

Test Data Generation

Identify Test data from Data profiles

Create Test Data

3

Test Case Design

 

3.1

Test Coverage Matrix

Dependency

Draft

Review with QA/SM

3.2

Functional Test Cases

Prepare Draft test cases

Review with QA team

Upload in HP-ALM

Identify Test data from Data profiles

Create Test Data

3.3

Integration  Test Cases

Prepare Draft test cases

Review with QA team

Upload in HP-ALM

Identify Test data from Data profiles

Create Test Data

3.4

End-End  Test Cases

Prepare Draft test cases

Review with QA team

Upload in HP-ALM

Identify Test data from Data profiles

Create Test Data

3.5

ETL/Reporting  Test Cases

Prepare Draft test cases

Review with QA team

Upload in HP-ALM

Identify Test data from Data profiles

Create Test Data

3.6

Regression Test Cases

Prepare Draft test cases

Review with QA team

Upload in HP-ALM

Identify Test data from Data profiles

Create Test Data

3.7

Performance Test Design & Scripting

Understanding the workflow

Creation/development scripting for workflow

Enhancing/Customizing script

Validation in SIT/Perf env

Update data parameter file for each script

Validation of existing scripts

Existing script maintenance

 

 

Test Data Identification and Creation/Set up

4

Test Automation

 

4.1

Test Script Preparation

Identify automation test cases

Enable/set framework and access

Test script draft

Existing script identification

Existing script Maintenance

5

Environment Readiness – QA

 

5.1

Environment Readiness

Key dependency

Submit Smartsheet – Environment Intake

Access raised and completed

Test Data required for Batch

Smoke Testing

5.2

Performance Environment Readiness

Submit Smartsheet – Environment Intake and Data Back up’s

Code Deployment into Perf env (as applicable)

Configuration changes and Pre requisite required.

Data Backup (Gold/Platinum/Titanium)

Environment shakedown testing

6

Test Execution – SIT

 

6.1

Cycle_1

Dependency

Application Test Cases

Integration Test Cases

ETL/Reporting Test Cases

Defect Remediation

6.2

Cycle_2

Dependency

Application Test Cases

Integration Test Cases

ETL/Reporting Test Cases

Defect Remediation

6.3

Cycle_3(Regression)

Clean Regression

Defect Remediation

6.4

BAT Support

Support Bat Test Plan

Support BAT HPALM activities

Defect Triage

Test Data for BAT

6.5

PPD Testing

Dependency

PPD Project Regression Testing

6.6

Performance Testing – Baseline Testing

Execute Baseline Scripts

Performance Monitoring and Metric

Results validation

Defect Remediation

Data Restore

6.7

Performance Testing – Cycle 1(multiple Runs)

Execute Cycle 1

Performance Monitoring and Metric analysis

Results validation

Defect Remediation

Data Backup/Restore

6.8

Performance Testing – Cycle 2(multiple Runs)

Execute Cycle 2

Performance Monitoring and Metric

Results validation

Draft

Data Backup/Restore

6.9

Roll back testing

Dependency

Baseline testing

Rollback testing

7

Test Closure

 

7.1

SIT Test Summary Closure Report & Sign off

Draft

Review with QA/SM

Review with IT Project team

Review with Business

SIT Closure report Sign off

7.2

Performance Test Closure

Consolidation of Perf monitoring metrics/Loadrunner results

Draft

Review with QA/SM

Review with IT Project team

Review with Business

Performance Closure report Sign off

8

Production Readiness

 

8.1

QA Production Checklist

Draft

Review with QA/SM and Sign off from SM

Review with Production readiness team

Closure

8.2

Knowledge Transfer

KT/Transition to Product QA Team

All Project Related document in Teams path

9

Warranty Support

 

9.1

Warranty Support

Warranty release activities

 

 

 