QA Project Plan
|
# |
Major/Minor
Milestones |
Tasks
(Additional tasks to be added/modified
as per project needs) |
|
1 |
QA Resource Onboarding |
|
|
1.1 |
|
QA Team Onboarding |
|
1.2 |
|
System and Environment Access Provided |
|
2 |
Test Planning |
|
|
2.1 |
Requirement Analysis |
Tasks/Dependency |
|
BRD Walkthrough |
||
|
SAD Walkthrough |
||
|
NFR Requirements & Gap Analysis |
||
|
Walkthrough Completed |
||
|
2.2 |
Test Strategy |
Draft |
|
Review with SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
Test Strategy Sign off |
||
|
2.3 |
SIT Test Plan |
Draft |
|
Review with QA/SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
Test Plan Sign off |
||
|
2.4 |
Performance Test Planning |
Draft Test Plan document preparation |
|
Performance Scop/Scenario preparation and review |
||
|
Workload Model |
||
|
Review with QA/SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
Engage Support(Customer Infra, Networking, Application) team for
performance monitoring |
||
|
Engage support team for databack/restore required and duration |
||
|
Test Plan Sign off |
||
|
2.5 |
QA-De-identification Strategy |
Draft |
|
Review with QA/SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
DI-Strategy Sign off |
||
|
2.6 |
Test Data Generation |
Identify Test data from Data profiles |
|
Create Test Data |
||
|
3 |
Test Case Design |
|
|
3.1 |
Test Coverage Matrix |
Dependency |
|
Draft |
||
|
Review with QA/SM |
||
|
3.2 |
Functional Test Cases |
Prepare Draft test cases |
|
Review with QA team |
||
|
Upload in HP-ALM |
||
|
Identify Test data from Data profiles |
||
|
Create Test Data |
||
|
3.3 |
Integration Test Cases |
Prepare Draft test cases |
|
Review with QA team |
||
|
Upload in HP-ALM |
||
|
Identify Test data from Data profiles |
||
|
Create Test Data |
||
|
3.4 |
End-End Test Cases |
Prepare Draft test cases |
|
Review with QA team |
||
|
Upload in HP-ALM |
||
|
Identify Test data from Data profiles |
||
|
Create Test Data |
||
|
3.5 |
ETL/Reporting Test Cases |
Prepare Draft test cases |
|
Review with QA team |
||
|
Upload in HP-ALM |
||
|
Identify Test data from Data profiles |
||
|
Create Test Data |
||
|
3.6 |
Regression Test Cases |
Prepare Draft test cases |
|
Review with QA team |
||
|
Upload in HP-ALM |
||
|
Identify Test data from Data profiles |
||
|
Create Test Data |
||
|
3.7 |
Performance Test Design & Scripting |
Understanding the workflow |
|
Creation/development scripting for workflow |
||
|
Enhancing/Customizing script |
||
|
Validation in SIT/Perf env |
||
|
Update data parameter file for each script |
||
|
Validation of existing scripts |
||
|
Existing script maintenance |
||
|
|
|
Test Data Identification and Creation/Set up |
|
4 |
Test Automation |
|
|
4.1 |
Test Script Preparation |
Identify automation test cases |
|
Enable/set framework and access |
||
|
Test script draft |
||
|
Existing script identification |
||
|
Existing script Maintenance |
||
|
5 |
Environment Readiness – QA |
|
|
5.1 |
Environment Readiness |
Key dependency |
|
Submit Smartsheet – Environment Intake |
||
|
Access raised and completed |
||
|
Test Data required for Batch |
||
|
Smoke Testing |
||
|
5.2 |
Performance Environment Readiness |
Submit Smartsheet – Environment Intake and Data Back up’s |
|
Code Deployment into Perf env (as applicable) |
||
|
Configuration changes and Pre requisite required. |
||
|
Data Backup (Gold/Platinum/Titanium) |
||
|
Environment shakedown testing |
||
|
6 |
Test Execution – SIT |
|
|
6.1 |
Cycle_1 |
Dependency |
|
Application Test Cases |
||
|
Integration Test Cases |
||
|
ETL/Reporting Test Cases |
||
|
Defect Remediation |
||
|
6.2 |
Cycle_2 |
Dependency |
|
Application Test Cases |
||
|
Integration Test Cases |
||
|
ETL/Reporting Test Cases |
||
|
Defect Remediation |
||
|
6.3 |
Cycle_3(Regression) |
Clean Regression |
|
Defect Remediation |
||
|
6.4 |
BAT Support |
Support Bat Test Plan |
|
Support BAT HPALM activities |
||
|
Defect Triage |
||
|
Test Data for BAT |
||
|
6.5 |
PPD Testing |
Dependency |
|
PPD Project Regression Testing |
||
|
6.6 |
Performance Testing – Baseline Testing |
Execute Baseline Scripts |
|
Performance Monitoring and Metric |
||
|
Results validation |
||
|
Defect Remediation |
||
|
Data Restore |
||
|
6.7 |
Performance Testing – Cycle 1(multiple Runs) |
Execute Cycle 1 |
|
Performance Monitoring and Metric analysis |
||
|
Results validation |
||
|
Defect Remediation |
||
|
Data Backup/Restore |
||
|
6.8 |
Performance Testing – Cycle 2(multiple Runs) |
Execute Cycle 2 |
|
Performance Monitoring and Metric |
||
|
Results validation |
||
|
Draft |
||
|
Data Backup/Restore |
||
|
6.9 |
Roll back testing |
Dependency |
|
Baseline testing |
||
|
Rollback testing |
||
|
7 |
Test Closure |
|
|
7.1 |
SIT Test Summary Closure Report & Sign off |
Draft |
|
Review with QA/SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
SIT Closure report Sign off |
||
|
7.2 |
Performance Test Closure |
Consolidation of Perf monitoring metrics/Loadrunner results |
|
Draft |
||
|
Review with QA/SM |
||
|
Review with IT Project team |
||
|
Review with Business |
||
|
Performance Closure report Sign off |
||
|
8 |
Production Readiness |
|
|
8.1 |
QA Production Checklist |
Draft |
|
Review with QA/SM and Sign off from SM |
||
|
Review with Production readiness team |
||
|
Closure |
||
|
8.2 |
Knowledge Transfer |
KT/Transition to Product QA Team |
|
All Project Related document in Teams path |
||
|
9 |
Warranty Support |
|
|
9.1 |
Warranty Support |
Warranty release activities |
|
|
|
|
No comments: